Clayton County plans to remove golf facilities from the North Clayton High project
What happened
District staff said they plan to remove the golf portion of the North Clayton High School construction project and bring a cost-reducing contract change to the board in coming months. Staff also described shifting the next round of capital recommendations toward roofs and HVAC as enrollment declines; no golf-scope removal was approved at this meeting.
Why it matters to families
The proposed change would reduce the facilities included in the new high-school project and redirect capital planning toward existing-building needs.
The evidence
At 1:20:01–1:20:15 staff said they were looking to remove the golf scope and bring a roughly $9 million deductive change order covering that and other project initiatives. At 1:25:53–1:27:09 staff clarified the scope reductions remain recommendations and the North Clayton change order would return in coming months, while future capital work would emphasize roofs and HVAC. At 1:23:23–1:23:29 the North Clayton contract was identified as $228 million; this is not the remaining balance. Later questions at 1:45:39–1:46:13 requested details rather than approving removal. The meeting ended without a construction-scope vote.
The source
Clayton County Board of Education Work Session | October 26, 2026See the full record for Clayton County.