Seismic upgrade of elementary and preschool wing underway

Facilities
Excerpt from Dufur School District board: June 2nd, 2026 Regular School Board Meeting for Seismic upgrade of elementary and preschool wing…
Official source excerpt: Dufur School District board: June 2nd, 2026 Regular School Board Meeting; editorial caption by Our School Board · source-evidence

What happened

Using a state seismic rehabilitation grant, Dufur is reinforcing the elementary and preschool wing of the K-12 school. On June 2, 2026 the board picked Griffin Construction as construction manager/general contractor for phase 2, and investigation work in classrooms began in October.

Why it matters to families

Work will happen inside classrooms that elementary and preschool students use, and crews will cut small holes in ceilings and floors for testing. The project is meant to make the building safer in an earthquake and may improve heating efficiency.

The evidence

December 2, 2025 recording: board approves the CMGC procurement method for the seismic project. June 2, 2026 recording: motion to approve Griffin Construction as CMGC for 'seismic rehabilitation phase 2'. October 6, 2026 recording: crews coming on October 12 to investigate and take samples in the elementary and preschool wing. Taken from auto-captions.

The source

June 2, 2026 board meeting (recording)

Share this story

Help your community stay informed about the decisions that affect your schools.

Get alerts like this for Dufur School District 29

We read every agenda, packet, and set of minutes, and write up the decisions that affect families — each one linked to the document it came from, the moment it's public.

Get personalized alerts