High school bathroom reopening delayed after structural damage was uncovered

What happened
Renovated bathrooms at G. Ray Bodley High School remained unavailable after contractors found an undersized floor slab and rotted decking. At the September 22 meeting, the construction manager said the structural issue had been addressed and crews were aiming to finish around October 5, with earlier partial reopening if possible.
Why it matters to families
Students began the school year with reduced bathroom access, and the newly reported structural problem explains the continuing renovation delay. The reopening date was a contractor target rather than a confirmed completion.
The evidence
September 22 transcript, 00:19:21–00:20:44: asked about the high school bathrooms, the construction manager said seven tile workers were on site, a large structural issue had caused the delay, most of the slab was undersized and much of the decking was rotted, probably from prolonged leaking. He said the design team produced a resolution within three or four days and crews were targeting the 5th, with possible earlier turnover of one floor. At 00:46:00–00:46:14 the board again acknowledged the unfinished bathrooms and structural changes. The remainder of the meeting contained no revised completion date. Historical September 8 document 164618 also reported high school bathroom work still underway; the published district overview identifies the high school as G. Ray Bodley High School.
The source
Board of Education Meeting 9/22/26 @ 6PM (At the Ed Center on 4th Street)See the full record for Fulton City School District.