ourschoolboard.org Find my school

District overview

Garfield Public School District

How Garfield schools are paid for, who decides, and what is being built or cut right now

Where does the money come from?

Two dollars in three come from the state, and every new aid dollar is already spent

Garfield runs on state aid. Of the $131.6 million operating budget the board adopted for 2026-2027, $87.9 million is state aid and $39.2 million is the local property tax levy, so roughly two dollars in three arrive from Trenton, most of it as equalisation aid of $75.9 million. State aid rose 6 percent, or $4,973,090, for 2026-2027, and the district's own budget presentation shows that entire increase already consumed by three costs it does not control: health insurance up $3,580,960, charter school tuition up $1,214,655 and energy up $850,354. Funding everything the district was contractually committed to would have needed a 10.2 percent levy increase, so the board cut $6.2 million, removed about 60 positions and settled on a 5 percent levy, adding $245 a year to the bill on an average home. Ten percent of the whole budget, $13.7 million, leaves the district as charter school tuition.

State aid is two thirds of the budget

$87,924,588 of the $131,556,546 operating budget for 2026-2027, of which $75,868,910 is equalisation aid. The local levy supplies $39,173,640. A thin year in Trenton would land far harder here than a levy decision.

The whole aid increase went on three bills

State aid rose $4,973,090. Health insurance rose $3,580,960, charter tuition $1,214,655 and energy $850,354, together $5,645,969, more than the increase. Employee benefits rise from 33.73 percent of salaries to 40.87 percent.

About 60 positions were removed

The budget presentation records a position control adjustment of roughly 60 fewer positions saving nearly $7 million, after the board cut $6.2 million to bring a needed 10.2 percent levy increase down to 5 percent.

$13.7 million follows children to charter schools

Charter tuition is 10 percent of the overall budget and rose 10 percent in a year, from $9.7 million in 2022-2023. The business administrator told the board ten cents of every state aid dollar goes straight out to charters.

There is no written meeting record

Garfield publishes neither board agendas nor minutes as documents. Its Board Meetings and Archived Meeting Minutes pages carry no files, and the BoardDocs site its board page links is empty. What the district does publish is a recording of every board meeting, so everything on this page about a meeting comes from the video.

None of this means the district is failing. It spends $693 per pupil less than the state's regional limit on administration, it adopted its budget on time after an advertised hearing, it is building a new school through state School Development Authority funding rather than local borrowing, and it has been adding programmes, from career academies to a first competitive esports season, through grant and title money rather than the local levy. The squeeze described here is mostly insurance, energy and charter enrolment, none of which the board sets.

Where the district stands

Adopted operating budget, 2026-2027verified
131,556,546 USD
Total revenues and sources, 2026-2027verified
144,611,368 USD
State aid, 2026-2027verified
87,924,588 USD
Equalisation aid, 2026-2027verified
75,868,910 USD
Local tax levy, 2026-2027verified
39,173,640 USD
Share of the operating budget from state aidcontext
66.8 percent

Calculated: $87,924,588 of state aid against the $131,556,546 operating budget, both from the adopted budget, so the ratio is context rather than a reported figure.

School tax bill on an average $285,000 home, 2026-2027, up from $4,916verified
5,161 USD
Tuition paid to charter schools, 2026-2027verified
13,732,856 USD
Positions removed to balance the 2026-2027 budgetverified
60 positions
Special education tuition, 2026-2027verified
9,167,188 USD
Pupils sent to other districts for special education, estimated October 2026, up from 43verified
103 students
Overall enrolment including out-of-district, charter and technical, March 2026verified
5,514 students
Total budgetary comparative per-pupil cost, 2026-2027, down from $22,497verified
22,028 USD
Administrative cost per pupil below the state regional limitverified
693 USD
Board minutes or agendas published as documents, out of 15 recorded meetings in the yearcontext
0 documents

Checked on the district's Board Meetings and Archived Meeting Minutes pages over ordinary HTTP and through a proxied browser render, and on the BoardDocs tenant the board page links, which returned an empty site.

District schoolscontext
11 schools

From the federal NCES Common Core of Data 2025-26 preliminary directory, not a district document.

Major projects

New School 5 on Outwater Lane

Under construction, final leg

A new school funded through the New Jersey School Development Authority is going up on Outwater Lane. In November 2025 the site was still a pile of dirt; by February 2026 the construction manager was presenting on it, in March a beam-signing ceremony was held, and by August 2026 the superintendent described the last leg of the project. The district says it has already been promised another new building in the last cycle of School Development Authority funding, and that once School 5 opens the idea would most likely be to close a school to offset some of the running costs. Parking at the new site is a problem the superintendent has raised at almost every meeting.

Next: Opening the building, and with it a decision the district has flagged but not made about closing another school; no closure has been proposed or named.
  1. Superintendent says structures will soon be going up at the site, still a pile of dirt
  2. Pascack Construction presents on School 5 and the long range facilities plan
  3. Superintendent says that once School 5 opens the idea would most likely be to close a school
  4. Superintendent reports the last leg of the project

Funding

New Jersey School Development Authority state funding, not local borrowing; the district has not published an operating cost projection for the new building

Device ban and updated dress code for 2026-2027

Adopted for September 2026

Two regulations changed the school day from September 2026. Regulation 5516 requires every student from kindergarten to grade 12 to keep internet-enabled devices powered off and stored all day, with use only where administration authorises it for an instructional need and a documented medical accommodation route. Regulation 5511 keeps district-approved uniform shirts and black or khaki bottoms as the standard and clarifies footwear rules and prohibitions on prominent logos, pyjamas and jeans except on dress-down days, with administrative review for hardship, religious or medical needs.

Next: Building-specific guidance and frequently asked questions from principals, which the superintendent said would follow before the school year opened.
  1. Superintendent sets out the locker-or-leave-it phone protocol to the board
  2. Board adopts first reading of Regulations 5516 and 5511; superintendent writes to families
  3. Second and final reading scheduled, taking effect for 2026-2027

Funding

No separate appropriation identified; the superintendent said the district does not think it needs pouches or special devices

Expanding special education programmes in district

Planned for 2026-2027

With pupils sent to other districts for special education rising from 43 to an estimated 103 and special education tuition up $1,287,623 to $9,167,188, the district's stated goals for 2026-2027 are to grow its Life Skills, autism and extended school year programmes, increase least restrictive environment placements, and expand self-contained and resource centres in elementary and middle schools. It has already brought pre-kindergarten special education applied behaviour analysis services in house, saving $498,198.

Next: The October 15 enrolment count, which is when out-of-district placement numbers are fixed for funding purposes.
  1. Budget presentation sets out special education goals and the in-house pre-K ABA saving
  2. A parent tells the board local summer provision offers no adaptive classroom or special needs programme

Funding

Operating budget special education lines, with $498,198 already saved by bringing pre-K ABA services in house

Five-year technology plan and classroom AI tools

Under way

The district is replacing computers that cannot run Windows 11 under a five-year lease agreement and plan, and modernising platforms including PowerSchool, Renaissance, eduCLIMBER and Office 365. Alongside that it approved Brisk, an artificial-intelligence tool for teachers, in November 2025, and by May 2026 the superintendent described AI as being in everything, naming Brisk for lesson plans and AI portals including PowerBuddy. Student use is governed by Policy 2365, adopted April 2025.

Next: Continued rollout under the five-year technology agreement, and a proposal the superintendent said he would bring the board for virtual anatomy technology with an AI component.
  1. Superintendent describes a coming proposal for AI-assisted virtual anatomy technology
  2. Board approves Brisk, an AI programme for teachers
  3. Five-year computer lease brought to the board because existing machines cannot run Windows 11
  4. Superintendent tells the board the AI piece is in everything now

Funding

Five-year lease agreement for hardware inside the operating budget; some programme costs met from federal title funds rather than the local levy

Boilers, lighting and facility upgrades

Rolling programme

Separate from the new school, the district is working through its long range facilities plan with its construction manager: all three boilers were replaced by January 2026 along with an electrical panel, and the 2026-2027 goals list lighting upgrades districtwide, classroom and restroom renovation, outdoor space upgrades, bus depot enhancements, and electric car and bus charging stations funded by grant. Vendor services cover HVAC, electrical and fire alarm systems, integrated pest management, and water, lead and indoor air quality monitoring.

Next: The facility fix list the superintendent and business administrator prepared with the construction manager for board approval.
  1. All three boilers replaced and an electrical panel brought for approval after cold weather
  2. Construction manager presents the long range facilities plan projects
  3. Budget presentation sets out the 2026-2027 facilities goals

Funding

District facilities appropriation, which rises from $9,017,526 to $10,464,016 for 2026-2027, plus grant funding for charging stations

Recent news

Built from the Garfield Board of Education's own published record: the district's YouTube playlist of board meetings from October 2025 through September 2026, read as caption transcripts; the 2026-2027 advertised budget, user-friendly budget summary and board budget presentation; the superintendent's letter to families on the 2026-27 policy updates; the district's published policies on student device use and generative artificial intelligence; and the public notices, bids and committee assignments on its legal notices page.