District news
Whitehaven flood disrupts building systems as STEM classrooms await clearance
What happened
On Oct. 20, staff reported flooding at Whitehaven High School affecting electricity, phones and internet, with a next-day closure possible but unconfirmed. Students were also awaiting full use of the STEM addition while life-safety systems were connected; a later Nov. 10 update said flood damage was repaired but alarm synchronization still preceded student move-in.
Why it matters to families
The record documents a concrete disruption and a delay in access to new instructional space, while distinguishing the initial emergency from later repairs.
The evidence
Oct. 20 at 12:21–16:48: the superintendent said teachers had moved into the STEM building but daily full-capacity student use had not begun, pending intercom/fire-alarm sequencing with the main building. At 13:34–14:47 staff described substantial flooding in the MAIN building basement near electrical equipment and the boiler, affecting electricity, phones and internet; a possible next-day closure was still being assessed. The source does not confirm that closure occurred. A separately read Nov. 10 follow-up in document 164923 at 1:16:42–1:19:02 reported flood-related fire-system damage fixed, with STEM-to-main-building alarm programming planned for the following Tuesday and student move-in waiting for synchronization. That is a later reported repair and planned clearance, not proof the STEM addition was already occupied.
The source
MSCS Board Committee / Board Work Session 10-20-26See the full record for Memphis-Shelby County Schools.
Get alerts like this for Memphis-Shelby County Schools
We read every agenda, packet, and set of minutes, and write up the decisions that affect families — each one linked to the document it came from, the moment it's public.
Get personalized alerts