Moraga plans $16 million modernization phase at Camino Pablo and Los Perales

Facilities
Excerpt from Regular Governing Board Meeting  with Closed Session - Oct 13 2026 for Moraga plans $16 million modernization phase at…
Official source excerpt: Regular Governing Board Meeting with Closed Session - Oct 13 2026; editorial caption by Our School Board · source-evidence

What happened

Phase 2 Measure D modernizations at Camino Pablo and Los Perales remain a district priority, with construction targeted to start in June 2027. The planning budget is $8 million per campus—$6 million in estimated construction costs and $2 million in soft costs—with design completion targeted for October 2026 and state review submission for late November.

Why it matters to families

This outlines a substantial planned investment and timeline for two elementary campuses, though the presentation is a planning update rather than final approval of construction contracts or detailed project scope.

The evidence

At the October 13, 2026 meeting, the Measure D update said Phase 2 modernizations at Camino Pablo and Los Perales remain prioritized over secondary scope items, with a budget of $8 million per site ($6 million estimated GMP and $2 million soft costs). Design completion was scheduled for October 2026, DSA submission for late November 2026, and a June 2027 construction start. The same update said administration was exploring alternative funding for technology upgrades.

The source

Regular Governing Board Meeting with Closed Session - Oct 13 2026

Get alerts like this for Moraga School District

We read every agenda, packet, and set of minutes, and write up the decisions that affect families — each one linked to the document it came from, the moment it's public.

Get personalized alerts