Norwich targets July completion for Moriarty and Uncas schools

Facilities

What happened

Norwich expects the new Moriarty and Uncas school buildings to be completed by the end of July ahead of the 2027–28 redistricting. Uncas was about two weeks behind after a steel-delivery delay, with additional work planned to recover the schedule.

Why it matters to families

Completion timing affects the district’s move into its new elementary-school configuration.

The evidence

At33:38–34:13superintendentgivesend-of-Julytargetandsteel-deliverydelay/overtime+additionalworkersintendedtoalignMoriartyandUncas—notalreadycaughtup. CurrentNov2026/27–28moveestablishJuly2027notJuly2026. PriorSeptember8source166555constructionquery[70499,72499]1:01:52–1:02:05confirmsMoriarty/Uncas/GreenvillealreadyUNDERCONSTRUCTION;[68366,70366]StantonALREADYOPENEDon timewithapprovedextraweekandnonoperationalpunchlist,notnewNovemberopening. November58:07–26beamsdone/toursfuturelate spring—notcompletedschools. ExactfullcanonicalnamesnotverifiedbeyondshortMoriarty/Uncasreferences;[]limitedtwocampuses. Noexactbudget/guaranteedoccupancy/noGreenvillecompletiondateinvented.

The source

Norwich Public Schools Board of Education Meeting - 11/10/2026

Share this story

Help your community stay informed about the decisions that affect your schools.

Get alerts like this for Norwich School District

We read every agenda, packet, and set of minutes, and write up the decisions that affect families — each one linked to the document it came from, the moment it's public.

Get personalized alerts