ourschoolboard.org

District news

Pleasant Valley High plans winter-break demolition and phased restroom work

Facilities

What happened

Pleasant Valley High’s construction team plans demolition and abatement during Christmas break, followed by restroom reconstruction one area at a time while classes continue. Staff said work areas would be walled off, accessible restrooms and elevators would remain usable, and the schedule would be reconsidered if it disrupts instruction.

Why it matters to families

Students will share parts of the campus with an active construction project, with temporary work zones and scheduled material movement intended to protect access and learning.

The evidence

October12 recording22:43–24:11 describes ongoing high-school construction and a connecting ramp giving access to foods/FCS and preschool lab areas. At24:25–25:57 staff acknowledges labor/weather schedule challenges. At26:43–28:41 staff explains Christmas-break demolition and abatement, phasedrestrooms, temporarywalls, controlled haulingtimes and possible rescheduling to offhours/springbreak if interference occurs. Staff explicitly says accessible restrooms/stairways/elevators remain available. This is a construction-phase operating plan, not evidence of hazardous exposure while students are present or a new contractaward.

The source

Pleasant Valley Community School District School Board Meeting - October 12, 2026

Share this story

Help your community stay informed about the decisions that affect your schools.

Get alerts like this for Pleasant Valley Comm School District

We read every agenda, packet, and set of minutes, and write up the decisions that affect families — each one linked to the document it came from, the moment it's public.

Get personalized alerts