Gladiator Stadium rebuild is running late
What happened
Workers are building new locker rooms, concession stands, restrooms and an elevator at Gladiator Stadium. In July 2026, the architect said the work was about 75% done. Rain and a small tornado added 25 days of delay, so the finish date moved from September 23 to October 19, 2026.
Why it matters to families
Restrooms and concessions were promised for the first home game on August 28. Locker rooms and the elevator would not be ready until later in the season. Spectators can use new ADA ramps and covered walkways.
The evidence
The official July 29, 2026 recording shows the architect's update under consent item 5D. It covers 75% completion, 25 delay days and substantial completion moving from September 23 to October 19, 2026. It also says restrooms and concessions would be released for the August 28 game. It is based on auto-generated captions.
The source
Regular Meeting of the Board of Trustees of Roma ISD, July 29, 2026 (recording)See the full record for Roma Independent School District.