Route 26 sidewalk project loses an additional crossing; final scope remains unsettled

Facilities

What happened

Officials report that DOT rejected an additional crosswalk in the long-planned sidewalk project near the Libby Hill school entrance. The town hopes to advance the project in summer 2027, but environmental review remains underway and rising costs will require a smaller project whose final scope has not been settled.

Why it matters to families

The project concerns walking access around the school entrance and middle-school crossing. Families should not assume the previously described additional lit crossing or the full original sidewalk plan will be built.

The evidence

November 4 recording, 1:36:23–1:36:50: environmental assessment review with HUD and Army Corps is nearing its end, engineering is ready, bid materials are being prepared, and summer 2027 is a town goal. At 1:37:20–1:38:11 officials recall the earlier sidewalk and lighting plan. This is immediately corrected at 1:38:15–1:38:40: DOT vetoed the additional crosswalk as too close to another crossing. At 1:38:40–1:39:25 the remaining sidewalk on the other side is undetermined, the project must be scaled back, definitive scope conversations have not occurred, and the district is holding a requested additional installment until work occurs. Do not repeat the earlier recalled crossing as an approved current feature or promise a construction date.

The source

November 4, 2026 – School Board Business Meeting

Share this story

Help your community stay informed about the decisions that affect your schools.

Get alerts like this for Rsu 15/Msad 15

We read every agenda, packet, and set of minutes, and write up the decisions that affect families — each one linked to the document it came from, the moment it's public.

Get personalized alerts