Board approves Crest View renovation plans; project is $800,000 over budget
What happened
The board approved the plans, specifications and estimated cost for the Crest View renovation. The project is currently projected to exceed its individual budget by $800,000, with added scope after the pre-bond building review cited as the reason.
Why it matters to families
The approval moves a bond-funded school renovation forward, while the overage leaves the district to manage scope and costs as bids come in. Officials said the first four projects together were about 13% below budget at this stage, but no final funding transfer was committed.
The evidence
During the Nov. 23 meeting, the board closed the public hearing and approved the Crest View renovation plans, specifications and estimated cost. In discussion, staff said added scope following meetings with building user groups had put the project about $800,000 over its budget; the first four bond projects combined were about 13% under budget, and a possible front-office work alternate was still being considered. The approval motion carried. Transcript: 32:00–39:05.
Make Change
To explore changing this project, reach out to a school board member—they’re a useful first contact.
The source
WDMCS Board of Education Meeting (Nov. 23, 2026)See the full record for West Des Moines Comm School District.