Board scales back Valley Park facility fix from $7.5M to $1.5M, splits project into phases
What happened
At the August 26, 2026 meeting, the Board approved an amendment to the FY2028-2033 Six-Year Capital Improvement Plan that revises Project No. 2, the Valley Park Code and Life Safety Upgrades, from an estimated $7,500,000 down to a Phase 1 estimate of $1,500,000, addressing only the most urgent egress and accessibility corrections at the shared Ketchikan Charter School/TSAS building.
Why it matters to families
Valley Park has documented structural, code, life-safety, and accessibility deficiencies (including a recent emergency repair to exterior egress stairs). Scaling the project back to a first phase means major accessibility issues \u2014 including an inaccessible elevator and lower-level classrooms serving two schools \u2014 will not be fully addressed in the near term, and the full cost of remaining work (later phases estimated near $5.2M-$6.3M) will need future funding decisions.
The evidence
Agenda item 11b states the amendment 'revises the estimated cost from $7,500,000 to $1,500,000' for 'Phase 1' addressing 'the facility's most urgent egress and accessibility corrections,' with the plan adopted by Board motion on August 26, 2026.
The source
25. August 26, 2026 Regular Meeting — 10. Amended KGBSD 6-Year CIP.docx.pdfSee the full record for Ketchikan Gateway Borough School District.