ourschoolboard.org Find my school

District overview

Marblehead Public Schools

Governance, budget pressure, and major facilities work in Marblehead Public Schools.

Who makes district-wide decisions?

Five-member elected School Committee

The Marblehead School Committee sets district policy, approves budgets and fees, oversees the superintendent, and votes on major contracts. Its public archive includes full-committee meetings plus budget, facilities, policy, and goals subcommittee work.

Public contact

The committee publishes a shared email address and individual public member emails.

Budget pressure

FY27 planning materials documented existing staffing reductions and several options for a further $1.5 million gap.

Facilities oversight

The committee is overseeing major high-school roof/HVAC work and remediation of roofing damage at Veterans Middle School.

The March budget packet presents options and projections; it does not by itself establish which final combination was ultimately funded.

Where the district stands

Official documents reviewedverified
60 documents
Projected FY27 budget with $1.5M restorationverified
$49.12M dollars
High-school roof/HVAC contractverified
$8.97M dollars

Major projects

Marblehead High School roof and HVAC project

Contract awarded; construction oversight underway

Pre-functional HVAC testing and long-lead equipment procurement were underway.

Next: Substantial completion was targeted for October 2026.
  1. School Committee awarded the $8.97 million general contract.
  2. Pre-functional HVAC testing and long-lead equipment procurement were underway.

Funding

Debt-exclusion project budget

FY27 budget resolution

Multiple gap-closing options documented

The committee reviewed options for an additional $1.5 million reduction.

Next: Confirm the final funded budget and which staffing or financing options were adopted.
  1. The superintendent presented the proposed FY27 budget.
  2. The committee reviewed options for an additional $1.5 million reduction.

Funding

Town appropriation, with an override and other financing options considered

Local elections & school board members

Elections & votes

Debt exclusionPassed

Debt exclusion for Marblehead High School roof project

Marblehead · $11,090,000

At the June 10, 2025 town election, Marblehead voters approved Question 2, a Proposition 2 1/2 debt exclusion funding the Marblehead High School roof (and related HVAC) replacement project, reported at about $11.09 million, by 4,436 votes to 1,579. A companion Question 1 debt exclusion for the Mary Alley Building also passed, 4,088 to 1,857.

Official source · verified Aug 19, 2026

School board members

Get alerts for Marblehead Public Schools

We read every agenda, packet, recording, and set of minutes, and write up the decisions that affect families — each one linked to the document it came from.

View alerts for this district