Funding structure, how it compares to peers, and where major projects stand.

Photograph taken of Paintsville High School from Second Street
Steven Williamson (HiB2Bornot2B) - talk ▓▒░ Go Big Blue! ░▒▓ · public-domain

How Paintsville’s budget, construction and Board decisions fit together

The Board approved an FY2027 tentative budget, managed a grant-funded multi-phase STEAM Academy project, closed out a district HVAC renovation and revised student technology and health rules during the reviewed period.

District resources include local property and utility taxes, Kentucky SEEK and other state support, federal programs, food-service revenue, restricted capital funds, bond proceeds and project grants. The May tentative budget is a planning document rather than actual year-end spending. Paid-warrant records show approved monthly checks, but they do not establish complete annual expenditures or a comparable per-pupil amount.

The FY2027 tentative General Fund is $9.68 million

The May budget shows $9,677,125.51 in both General Fund revenues and expenditures, including a $1,602,058.51 beginning balance and $1.546 million in state on-behalf payments. It is a tentative budget, not actual spending.

The STEAM Academy BG-1 totals $8.44 million

The February revision identifies four grants—$2.5 million, $3 million, $300,000 and $2.64 million—as the funding sources for the first two phases. The Board later advanced design and approved seven May change orders netting $534,467.91.

The later HVAC closeout form reports $5.32 million

The April BG-5 for BG23-402 lists $5,324,716.97 in final costs against $5,582,619 in current BG-1 costs, leaving $257,902.03. A January form for the same named project gives different figures; the reviewed record does not explain the change.

The separate PES HVAC repair rose to $181,007

After an October emergency declaration and November quote approval, the January BG-1 budgeted $162,000. The April revised form raised the project to $181,007, funded with General Fund cash.

Current rules address phones and generative AI

Policy 09.4261 limits personal-device use during instructional time with stated exceptions. Policy 08.2323 requires safeguards and responsible-use procedures for AI and generative AI.

Available records include monthly paid-warrant totals and budget plans, but no audited FY2026 annual financial report. This page does not convert planning totals or monthly checks into annual actual spending or per-pupil expenditure.

Where the district stands

FY2027 tentative General Fundverified
9,677,125.51 dollars
STEAM Academy revised BG-1verified
8,440,000 dollars
Net May STEAM change-order packageverified
534,467.91 dollars
April BG-5 reported HVAC final costverified
5,324,716.97 dollars

Major projects

Paintsville Independent STEAM Academy

Design and construction changes approved through May 2026

The $8.44 million Phase I-II BG-1 covers demolition, roof and facade work for a technical and creative education center. The Board approved schematic and design-development work, construction drawings and seven May change orders netting $534,467.91.

Next: Watch later Board records for construction progress, any further changes and final reconciliation.
  1. Board approved the revised $8.44 million BG-1 and schematic design.
  2. Board approved BG-3 and design-development documents.
  3. Board approved revised BG-3 and construction drawings.
  4. Board approved seven change orders.

Funding

Four grants listed in the BG-1: $2.5 million, $3 million, $300,000 and $2.64 million.

Paintsville Elementary HVAC emergency repair and upgrade

Revised BG-1 approved in April 2026

The Board declared an emergency after a water-line failure affected heat, approved a repair quote, and later approved a BG-1 covering replacement water lines and two mini-splits for network-equipment rooms.

Next: Watch later records for completion and actual final cost.
  1. Board declared the HVAC failure and repair an emergency.
  2. Board approved the emergency repair quote.
  3. Board approved an initial $162,000 BG-1.
  4. Board approved the revised $181,007 BG-1.

Funding

General Fund cash.

PES and PHS gym HVAC renovation

BG-5 closeout approved in April 2026

The April BG-5 for BG23-402 reports $5,324,716.97 in final costs and $257,902.03 remaining, with SFCC, FSPK bond and General Fund sources. The January saved form for the same named project instead reports $3,246,681.06 in final costs and $3,390,174.97 in utilized funds. The record does not reconcile those figures or establish a scope change.

Next: Obtain a corrected or reconciled project record explaining the January cost/funds mismatch and the later April totals.
  1. Board approved a BG-5 reporting $3,246,681.06 final cost; the same form lists $3,390,174.97 in funds utilized.
  2. Board approved a revised PES/PHS HVAC BG-1.
  3. Board approved a later BG-5 reporting $5,324,716.97 final cost for the same named BG23-402 project.

Funding

SFCC bond and cash sources, local FSPK bond proceeds, and $500,000 General Fund cash.

Based on substantive review of all 48 collected official originals: 12 KSBA Board action records, 33 supporting attachments and three current policies. The officially linked YouTube channel contains no Board recordings in the trailing-year window; the newest listed Board recordings are from June 2024.