Rochambeau School renovations are behind schedule

Facilities

What happened

The Rochambeau renovation missed its August 28, 2026 contract date. About five classrooms are still under construction, and the gym skylights will not be done until early winter at best.

Why it matters to families

Students and staff are in a building that is still being worked on. The district had to hire a third party to clean the building before school opened.

The evidence

The September 2026 capital projects presentation says the project's completion is behind schedule because of an abatement contractor problem and too few workers from two main contractors. Windows and the electric upgrade are done.

The source

Capital Projects Update, September 2026

Share this story

Help your community stay informed about the decisions that affect your schools.

Get alerts like this for White Plains City School District

We read every agenda, packet, and set of minutes, and write up the decisions that affect families — each one linked to the document it came from, the moment it's public.

Get personalized alerts