Jackson Independent School District

Funding structure, how it compares to peers, and where major projects stand.

Editorial graphic for Jackson Independent School District
Editorial caption by Our School Board; base: Carl Hårleman · public-domain

What the reviewed Board records establish

Approved Board minutes establish actions through July 28, 2026; SBDM minutes establish school-level actions through September 16; finance exhibits extend through September 2026.

The elected Board governs districtwide operations, while the Jackson City School SBDM Council makes documented school-level curriculum, staffing-recommendation, policy and activity-fund decisions. The FY2026 working budget balances $2,194,622.92 of General Fund sources and uses through a $350,972.92 beginning balance, $266,550 in local revenue, $1,572,100 in state revenue and $5,000 in federal revenue.

FY2026 General Fund receipts exceeded expenditures

The unaudited AFR reports $2,751,360.44 in receipts, including $127,983.40 in interfund transfers, versus $2,326,453.39 in expenditures. Total sources of $3,362,446.01 also include a $611,085.57 beginning balance; this is an unaudited report, not a deficit finding.

September cash reconciliation matched

The September reconciliation begins with $1,960,824.68, adds $255,491.26 in receipts, and records $108,275.91 in accounts-payable expenditures and $196,102.48 in payroll. After listed adjustments and deposits in transit, bank and MUNIS totals both equal $1,925,270.07.

SBDM identified math performance and intervention needs

September SBDM minutes say privately reviewed KSA math results were alarming. The council discussed DESMOS Math, teacher input, tutoring and other intervention strategies; no later source establishes results.

Current phone and AI policies apply districtwide

Phone policy generally bars instructional-time use with emergency and teacher exceptions. Electronic-media policy requires responsible AI procedures addressing safety, privacy, ethics and inspiration versus cheating.

Districtwide per-pupil spending remains unavailable

The finance exhibits provide district fund totals, but the reviewed sources do not pair audited districtwide spending with same-period enrollment. No per-pupil amount is calculated.

The Board archive has approved minutes through July 28; its August 25, September 14 and September 22 records are agenda-only. The finance page's latest working budget is labeled FY2026 even though Board minutes record FY2027 draft and tentative approvals, so no FY2027 working-budget total is claimed.

Where the district stands

Students enrolled as of July 22, 2026verified
359 students
FY2026 General Fund working-budget sources and usesverified
2,194,622.92 USD
FY2026 unaudited General Fund expendituresverified
2,326,453.39 USD
September 2026 reconciled bank and MUNIS balanceverified
1,925,270.07 USD

Major projects

Exterior Security and Access Control

Initial BG-1 and design contract approved; cost, funding and later construction action unverified

June minutes approve the initial BG-1 and an alternate-form design contract. July minutes say the BG-1 was being sent to KDE. The August agenda lists construction documents and an invoice, but no collected minutes or recording establishes those later outcomes.

Next: Approved August minutes, KDE approval or a construction contract would establish the next authorized phase, funding and cost.
  1. Board approved the initial BG-1 and alternate-form design contract.
  2. Officials reported the BG-1 was being sent to KDE.
  3. Agenda listed construction documents and an invoice; outcome unverified.

Funding

Not established in the collected records.

Kitchen upgrades

Work underway; two equipment items remained and no completion record was collected

Food-service equipment concerns were discussed in February, May minutes said kitchen work was beginning, and July minutes said only a wok and flexible nozzle remained. The collected records do not state cost, funding or final completion.

Next: A later facilities or food-service report would establish final completion and cost.
  1. Board discussed food-service equipment and vendors.
  2. Minutes reported kitchen work was beginning.
  3. Minutes reported only a wok and flexible nozzle remained.

Funding

Not established in the collected records.

Recent news

All 50 collected official originals were restored and hash-verified. Review covered 13 Board occurrences, 17 distinct Jackson City School SBDM occurrences, the linked 2026 Board calendar, five complete finance exhibits, three current policy originals and the official Board information page. No Board or SBDM recording or transcript archive was linked from the official sources.