What is shaping Millbrook's plans?
The Board adopted a $38.0 million 2026–27 budget proposal after closing an earlier $1 million gap, while advancing construction work at the middle and high schools.
Operating budget
The adopted $37,992,751 proposal included staffing and other reductions plus additional use of fund balance.
Capital work
The Board awarded five phase 1A contracts; that phase was about $450,000 over its $7.4 million budget while phase 1B was then projecting below budget.
Student policy
The 2025–26 code of conduct requires internet-enabled devices to be stored in lockers throughout the school day.
The meeting records are machine-generated transcripts of public recordings, not approved minutes. Unclear wording is not treated as proof, and three additional recordings had no available transcript.
What is on the public record
Major projects
Middle and high school capital improvements
Phase 1A contracts awardedThe Board awarded separate general, mechanical, electrical, plumbing, and window contracts for initial middle- and high-school work.
- District reports phase 1A ready for bidding
- Board awards phase 1A contracts
Funding
Voter-authorized capital project
Phase 1A bids totaled about $7.85 million against a $7.4 million phase budget; the full project authorization discussed by the Board was $63 million.
Recent news
Reviewed every available transcript collected from the district-linked YouTube channel for meetings in the trailing-year corpus.
Get alerts for Millbrook Central School District
We read every agenda, packet, and set of minutes, and write up the decisions that affect families — each one linked to the document it came from.
View alerts for this district