ourschoolboard.org Find my school

District overview

Millburn Township Public Schools

How Millburn Township Public Schools is funded, governed, and spending money right now

How is the district funded?

Mostly local property taxes, with a state cap on how fast that can grow

Like most New Jersey districts, Millburn is funded mainly by local property taxes, not the state. The board adopted a 2026-2027 budget totaling $126,534,180, and $109,919,521 of that -- about 87% -- comes from the local tax levy paid by Millburn Township property owners. State law normally caps how much that levy can grow each year at 2%. For 2026-2027, the state approved the district's request to exceed that cap because health insurance costs for staff rose by more than $3.65 million, allowing that amount to be added on top of the normal increase. Before final adoption, the board also cut a net 4 teaching positions, citing enrollment and schedule changes, bringing the total down from the $126,878,636 originally advertised.

$126.5M total 2026-27 budget

General Fund $117,639,367, Debt Service $6,781,578, Special Revenue $2,113,235 -- adopted May 4, 2026 after the board trimmed $344,456 from the originally advertised budget.

$109.9M local tax levy

About 87% of the total budget comes from Millburn Township property taxes.

Levy cap exceeded for health costs

The state approved a $3,653,160 increase above the normal 2% cap specifically to cover higher health-benefit premiums.

Two active bond referenda

The district still draws on voter-approved 2020 and 2023 referenda to fund capital projects, alongside pay-as-you-go capital reserve spending.

Exceeding the tax-levy cap does not mean the district is spending carelessly. State rules only allow it for specific, documented cost increases like health insurance, and the board also cut its own spending -- trimming positions rather than passing the full advertised increase through to taxpayers.

Where the district stands

2026-27 total budgetverified
$126,534,180 total
2026-27 local tax levyverified
$109,919,521 total
Tax-levy cap waiver for health costsverified
$3,653,160 total
District enrollmentverified
4,456 students
Year-over-year enrollment changeverified
-2.9% percent

K-12 enrollment fell from 4,589 (2024-25) to 4,456 (2025-26), a drop of 133 students. The decline was sharpest in the incoming 6th-grade cohort, down 16%.

Budget per studentcontext
$28,394 per pupil

Calculated as the $126,534,180 total 2026-27 budget divided by the 4,456 students enrolled as of October 2025. This covers the whole district budget, not just classroom instruction, and the two figures are from different points in time.

Board of Education seatscontext
9 members

Millburn's Board of Education has nine elected members serving staggered three-year terms.

Major projects

High School Athletic Fields (turf conversion + lighting)

Under construction

A joint project with Millburn Township to convert two multi-purpose fields plus Miller Field at Millburn High School from natural grass to artificial turf and add lighting, aimed at closing a 16% shortfall in usable playing hours. Presented in November 2025, the board signed a shared-services agreement and design contract in February 2026, and awarded the construction contract in July 2026 over some public objection to the project's environmental impact and the lack of a townwide referendum.

Next: Construction start date and completion timeline were not stated in the board records collected through July 2026.
  1. Joint presentation to the Board and Township Council; preliminary combined cost estimate ~$7.5M
  2. Shared-services agreement with the Township approved; $192,500 design contract awarded to EI Associates
  3. $5,666,283 construction contract awarded to Thomas & Sons Builders LLC

Funding

Joint project with Millburn Township; district's design contract paid from Capital Reserve

Millburn High School Roof B Replacement

Construction substantially complete

Replacement of a section of the Millburn High School roof, awarded after the two lowest bids were withdrawn or rejected for procedural defects.

Next: No further payment applications appeared in board records after May 4, 2026, suggesting the project is close to or fully complete.
  1. Public bid opening; lowest bidder withdrew, second-lowest bid rejected for a bond-form defect
  2. $1,324,300 contract awarded to Northeast Roof Maintenance, Inc.
  3. Final payment application approved

Funding

General Fund capital budget

Multi-year facilities capital program (HVAC, science labs, MHS auditorium)

Ongoing

A running program of HVAC upgrades, science-lab renovations, and the Millburn High School auditorium renovation, funded through capital reserve spending and the district's 2020 and 2023 voter-approved referenda. The auditorium renovation hosted its first production in March 2026.

Next: Payment applications for these referendum-funded projects continued through the most recent board meetings collected.
  1. Board approved change orders and payments for HVAC upgrades at multiple schools and the MHS science lab renovation
  2. MHS Auditorium Renovation payment application ($890,682.80) approved
  3. First production staged in the renovated MHS auditorium

Funding

Capital reserve and 2020/2023 voter-approved referenda

District cabinet and building-leadership transitions

In progress

Several senior leadership roles changed over the year: a new Millburn High School principal started in December 2025; Assistant Superintendent John Connolly left in mid-2026 to become Superintendent of Madison, NJ; Kyle Arlington was promoted to succeed him; and Dr. Anne Richardson moved from Washington Elementary principal to Middle School principal, both effective July 1, 2026.

Next: As of the district's most recent collected records (July 20, 2026), the Washington Elementary School principal vacancy created by Dr. Richardson's move had not yet been filled.
  1. Robert B. Nixon, Jr. begins as Millburn High School Principal
  2. Both Millburn High School Vice-Principal seats filled
  3. Board approves Richardson as Middle School Principal and Arlington as Assistant Superintendent, both effective July 1, 2026

Funding

Not applicable

Recent news

Recent alerts by topic

Every agenda in the collected 12-month corpus was downloaded and read in full -- Millburn's agendas print the complete text of each resolution the board votes on, not just a title. Minutes, presentations, and attachment packets were opened and read (using OCR where a file was a scanned, signed copy with no embedded text) whenever an item needed outcome confirmation, a dollar figure the agenda did not give, or was a candidate for an alert or an overview figure. For routine, unremarkable business, the agenda's resolution text is treated as the record of what the board considered.