ourschoolboard.org Find my school

District overview

Westerly Public Schools

How Westerly's schools are paid for, who decides, and what is being built right now

Where does the money come from, and who says yes?

A town-funded district: the School Committee writes the budget, but the Town of Westerly votes the money

Westerly Public Schools does not raise its own taxes. Each year the elected School Committee builds a budget and then asks the Town of Westerly for the local share, on top of the education aid Rhode Island sends every district through the state funding formula. Rhode Island law (R.I. Gen. Laws 16-2-21(a)) requires the School Committee and Town Council to sit down together before the budget is set, and Westerly held that joint meeting on December 15, 2025. For 2026-2027 the committee adopted a request that is $904,836 higher than the year before and also spends $400,000 of the district's fund balance, the savings carried over from past years. That combination is the thing to understand about Westerly's finances right now: the gap is being closed partly with one-time savings, and savings can only be spent once.

The town votes the local share

The School Committee adopts a budget and submits it to the town; it cannot levy taxes itself. The FY2027 budget went to the town on February 19, 2026 and was finally approved by the committee on June 17, 2026.

State aid moves, and it moved down

The Governor's preliminary state aid projection for FY2027 cut Westerly's aid by $172,443, reported to the committee on January 27, 2026. That gap has to be made up locally or absorbed.

Fund balance is doing real work

Beyond the $400,000 in the operating plan, the committee committed $180,759 to the turf field, $97,500 to electrical upgrades and $799,605 to the middle school roof out of fund balance during this year.

Seven members, all elected at large

Committee members are elected town-wide for four-year staggered terms, so there are no ward seats. Much of the detailed work happens first in the Finance and School Building subcommittees, whose minutes carry discussion the full committee's do not.

None of this means Westerly is in financial trouble. Monthly reports through the year showed a projected surplus rather than a deficit, $310,631 as of January 31, 2026 and $284,335 as of February 28, 2026, and the FY2025 audit was presented to the committee in public in April 2026.

Where the district stands

FY2027 increase requested from the Town of Westerlyverified
$904,836 USD
Fund balance used to close the FY2027 budgetverified
$400,000 USD
Change in the Governor's preliminary FY2027 state aid for Westerlyverified
-$172,443 USD
Fund balance committed to the Westerly Middle School roofverified
$799,605 USD

Phase 1 was estimated at $1,486,924 in the March 11, 2026 School Building Subcommittee minutes, so this commitment covers a little over half of it.

Meetings in the past year with minutes filed with the statecontext
46 of 55 meetings

Counted across every School Committee, School Building, Finance, Special Education Advisory and Health & Wellness meeting collected for this page. The nine without minutes are mostly very recent meetings, two ceremonies, a building tour, and one meeting cancelled for lack of a quorum.

Total enrollmentcontext
~2,100 students

Major projects

New State Street School

underway

A replacement State Street School was built on the same site while the old building stayed in use. Pupils and furniture were moved over the summer of 2026, and the old building is being demolished.

Next: Completion of the old building's demolition and the new traffic pattern for the 2026-2027 school year, which the superintendent described to the committee on July 15, 2026.
  1. Subcommittee approves a public address and clock system redesign and extra ventilation
  2. Construction reported on schedule, with monthly payments running over $1 million
  3. Moving contract awarded to Gentry Inc.; window glazing declared an unacceptable nonconforming condition
  4. Glass to be replaced at the contractor's expense
  5. Moving, disposal and dumpster invoices approved for the relocation
  6. Subcommittee holds a building tour of the completed school

Funding

Rhode Island school construction programme approvals through RIDE plus town capital funding; construction payments are approved meeting by meeting by the School Building Subcommittee

Dunn's Corners and Springbrook elementary renovations

closing out

Both elementary schools were rebuilt and reopened with ribbon cuttings on October 16, 2025. Certificates of substantial completion followed in January 2026, and the projects have been in closeout since, with disputes over a roof, a plumbing fault and an incorrect school sign.

Next: Final closeout of the remaining punch list items, including visitor and accessible parking and the window concerns committee members raised in June 2026.
  1. Seven-day completion letter authorised over the unfinished Springbrook roof
  2. Ribbon cuttings held at Springbrook and Dunn's Corners
  3. Certificates of substantial completion approved; an electrical subcontractor tells the subcommittee it has not been paid since September 2025
  4. Change order #17 of $242,847.38 approved for additional work
  5. Incorrect Dunn's Corners School sign to be replaced at the architect's expense

Funding

Rhode Island school construction programme plus town capital funding; change orders approved by the School Building Subcommittee

Westerly Middle School roof replacement, Phase 1

funded and starting

The middle school roof is being replaced in phases. Phase 1 was designed, sent to the state for approval, bid, and funded from district savings, with work scheduled to begin once the town released funding on July 1, 2026.

Next: Completion of Phase 1 roof work and a decision on funding the later phases.
  1. Subcommittee asks to restart Phase 1 of the roof replacement
  2. State submission approved and bid released; estimated cost $1,486,924, work to start July 1, 2026
  3. School Committee awards the bid and commits $799,605 of fund balance
  4. First architectural and engineering invoice for the project approved

Funding

$799,605 committed from district fund balance against a Phase 1 estimate of $1,486,924, subject to town funding

No-phone school day

adopted, starting September 2026

The committee updated its Electronic Communication Devices Policy 7500 in December 2025 and set implementation for September 2026. The high school ran a trial no-phone day in the spring, and the superintendent reported preparing students and parents for the change.

Next: The first full school year under the policy from September 2026, and the related Teacher/Student/Parent Electronic Communications Policy 2320 update listed for a first reading on August 19, 2026.
  1. Policy Subcommittee takes on the district cell phone policy
  2. Electronic Communication Devices Policy 7500 update adopted unanimously
  3. Superintendent confirms September 2026 implementation
  4. Trial no-phone day held at Westerly High School

Funding

No dedicated budget line; handled within existing school operations

Athletic eligibility policy

unresolved; being redrafted

Whether the district should set sports eligibility by biological sex has been argued at meetings all year. The committee directed a draft in December 2025, then rejected it two weeks later on legal advice. After a United States Supreme Court decision, the solicitor and superintendent said in July 2026 they would revive the earlier language.

Next: The Attorney General opinion the August 19, 2026 agenda requests, and any draft policy brought back for a first reading.
  1. Motion to turn the transgender student protocol into policy fails 2-5
  2. Committee directs the superintendent to draft an athletic eligibility policy, 5-2
  3. Proposed policy rejected 6-1 on the solicitor's advice
  4. Solicitor reports a Supreme Court decision and says prior language will be revived
  5. Agenda lists a request that counsel seek a Rhode Island Attorney General opinion

Funding

No budget line; legal costs sit within the district's existing solicitor arrangement

Recent news

Built from the complete set of meeting notices, agendas and minutes that the Westerly School Committee and its School Building, Finance, Special Education Local Advisory and Health & Wellness subcommittees filed with the Rhode Island Secretary of State's Open Meetings system between September 3, 2025 and August 31, 2026 - the statutory record under R.I. Gen. Laws Chapter 42-46 - together with the district's own School Committee page for governance identity and the National Center for Education Statistics for enrolment. Most filed minutes are scanned documents and were read using optical character recognition.

Get alerts for Westerly Public Schools

We read every agenda, packet, and set of minutes, and write up the decisions that affect families — each one linked to the document it came from.

View alerts for this district