Funding structure, how it compares to peers, and where major projects stand.

How RSU 74 is paid for and who decides

A four-town regional school unit where local taxes cover far more than the state minimum

RSU 74 serves Anson (including North Anson), Embden, New Portland and Solon in Somerset County. A 15-member Board of Directors drawn from those towns sets policy, hires the superintendent and writes the budget. Voters then approve the budget article by article at a district budget meeting in May. For 2026-27 they approved $13.3 million in spending, including $3.2 million in local money above what Maine's school funding formula (Essential Programs and Services) counts as needed.

Voters approve the budget

At the May 20, 2026 district budget meeting, residents approved all 20 warrant articles, including the $13,300,474 total and $3,205,397 in extra local funds (written ballot 22-1).

Four towns share the local cost

The 2026-27 local share required by the state formula was $3,898,667, split as Anson $1,229,387, Embden $1,256,713, New Portland $666,110 and Solon $746,457.

Board members represent towns

Directors are listed by town: Anson/North Anson, Embden, New Portland and Solon. Troy Dunphy chairs the board and Kevin Sousa is vice chair for 2026-27.

Four schools

Carrabec High School, Carrabec Community School, Garret Schenck School (Anson) and Solon Elementary School.

The extra local money is explained by the board as paying for class sizes, special education, activities and transportation that the state formula does not fully count. That is common in rural Maine and does not by itself mean the district overspends.

Where the district stands

2026-27 total budget approvedverified
13,300,474 USD
Local money above the state formula, 2026-27verified
3,205,397 USD
Special education budget, 2026-27verified
2,695,632 USD
Transportation and buses budget, 2026-27verified
1,136,855 USD
Approved budget per student (approx.)context
22,620 USD

Context: $13,300,474 divided by about 588 students (NCES enrollment). Includes all costs, such as transportation and special education.

Food service loss, 2025-26verified
44,584 USD
Schoolscontext
4 schools

Major projects

Finding a principal for Garret Schenck and Solon

interim leader proposed

The two elementary schools share one principal. After three changes since April, the superintendent proposed former principal Jean Butler as interim while the job is re-advertised.

Next: Board vote on the interim appointment and a new principal search.
  1. Principal Jean Butler's resignation reported
  2. Board approves Nathaniel White
  3. Board approves Amy McDaniel (11-1)
  4. McDaniel resigns effective immediately
  5. Interim appointment of Jean Butler on agenda

Funding

Operating budget (school administration)

LED lighting upgrade

mostly complete

A $533,051 lease-purchase of LED lighting. CCS and CHS were finished in time to keep the maximum Efficiency Maine refund; Solon was still waiting in September; Garret Schenck was removed in March.

Next: Completion at Solon Elementary.
  1. Board adopts lease-purchase resolution
  2. Garret Schenck removed from project
  3. CCS and CHS reported complete; Solon pending

Funding

Lease-purchase financing plus Efficiency Maine refund

Space for Pre-K and 3-year-olds

being studied

The restructure committee is looking for classroom space for 2027-28, when the district must serve 3-year-olds now served by Child Development Services. The 4-year-old program has had waiting lists, and 10 Pre-K students were transferred to other districts.

Next: Committee site visits and a recommendation before the 2027-28 budget.
  1. Restructure committee reviews space needs
  2. Next restructure committee meeting scheduled

Funding

Not yet identified

Bus replacement and the 10-year plan

planning for 2027-28 budget

The transportation director recommended one bus in the coming budget and two in 2027-28. The board was asked on Oct. 7 to let the district seek state permission for two buses, which must be done by the third week of November for state reimbursement.

Next: State permission request before late November 2026.
  1. Bids for 2 buses approved
  2. Activity bus capped at $92,204
  3. Request to seek state approval for 2 buses

Funding

Annual budget with later state reimbursement

Local elections & school board members

Elections & votes

Public votePassed

RSU 74 district budget meeting: 2026-27 school budget

Anson, Embden, New Portland, Solon · $13,300,474

Residents approved all 20 warrant articles, including a $13,300,474 total budget and $3,205,397 in additional local funds (written ballot 22-1). The board certified the vote on June 11, 2026.

Official source · verified Oct 26, 2026

School board members

Recent news

Board agendas and minutes posted as pages on the official RSU 74 website (carrabec.org), the superintendent's monthly board report, board and committee meeting schedules, and policy JICJ, collected Nov. 2025 through Oct. 2026.

Get alerts for RSU 74 / MSAD 74 (Carrabec)

We read every agenda, packet, recording, and set of minutes, and write up the decisions that affect families — each one linked to the document it came from.

Copy the RSS link into your feed reader to get new published alerts.