How South Huntington is funded, who decides, and what is being built

How is the district paid for, and who decides?

Locally taxed, voter-approved budget

South Huntington is a school district that sets its own tax levy. Seven elected trustees adopt a budget each spring and voters approve it in May. Most of the money comes from local property taxes; the state adds less than the district says it needs, and a state cap limits how fast the levy can grow.

Property taxes pay most of the bill

The 2026-27 budget is $227,993,621. Property taxes raise $132,569,124 (about 58%). State aid is an estimated $77,854,497 (about 34%), down 0.17% from the year before. Reserves ($4.29 million) and fund balance ($2.79 million) cover most of the rest.

State aid is frozen at last year's level

The district's Foundation Aid is on 'save-harmless': it gets the same dollars as the year before even though the formula would give less. The district says 56% of New York districts are in the same position. The state added only about 1% more aid in the final state budget.

A tax cap limits the levy, but assessments move the tax rate

The levy increase for 2026-27 was 2.44% in April, within the state cap. In September a large cut to the Walt Whitman Mall's assessment and payments in lieu of taxes on four parcels cut taxable value to about $40.2 million, so the estimated tax-rate increase rose from about 3% to about 6.4%.

A seven-member board with advisory committees

Seven trustees are elected by district voters each May, plus a student ex officio member. Audit, curriculum, facilities, policy and wellness committees only advise; the full board votes at meetings usually held on Wednesdays at 7:30 p.m.

The district reports clean annual audits, an unassigned fund balance at the 4% legal maximum, no layoffs or program cuts in 2026-27, and mostly low-risk internal audit results. A State Comptroller audit of credit cards, however, found weak controls in 2022-23.

Where the district stands

2026-27 adopted budgetverified
227,993,621 USD

Up 2.44% from $222,568,493 in 2025-26.

Property tax levy 2026-27 (as adopted in April)verified
132,569,124 USD

Up 2.44% from $129,415,032. A lower levy of about $131.3 million was taken up on Sept. 30, 2026 after assessment losses.

Estimated state aid 2026-27verified
77,854,497 USD

Down 0.17% from $77,989,261; district used conservative assumptions.

Estimated school tax-rate increase after Sept. 2026 assessment changesverified
6.4 percent

Versus about 3% (3,162.79 vs 3,069.24 per $1,000) when the budget was adopted. Figure is from the business office presentation in auto-generated captions.

Students served in-districtverified
5,600 students

'Roughly 5,600 students' and about 1,200 employees, including about 580 teachers.

Budget per student (derived)context
40,713 USD

Context only: $227,993,621 divided by about 5,600 students. It includes benefits, transportation, debt, capital transfers and BOCES, not just classroom spending.

Salaries plus benefits share of 2026-27 budgetcontext
73.7 percent

Derived from $110,998,639 salaries and $57,092,181 benefits in the district's budget brochure, divided by $227,993,621.

Unassigned fund balance (June 30, 2025)verified
8.9 million USD

About 4% of the next year's budget, the maximum New York allows.

Pre-K registrations for 2026-27verified
269 children

Up from 213 in March; the district was still enrolling.

Recommendations in State Comptroller credit-card auditverified
16 recommendations

Five findings; district officials generally disagreed with the recommendations.

Major projects

Silas Wood Pre-K Center (universal pre-K)

Opened September 2026; still enrolling

Silas Wood changed from the sixth-grade center to a standalone pre-K center for 3- and 4-year-olds with up to 15 classrooms, a second playground, and before- and after-school care run with the community partner SCOPE.

Next: Enrollment of seats by about Oct. 15, 2026, the date the district uses to count funded seats
  1. Board hears the pre-K center plan; registration to open Jan. 12 with no lottery
  2. Facilities committee plans a $250,000 second playground and door-lock choices
  3. Board awards the pre-K partner contract to SCOPE
  4. Board awards the second-playground contract
  5. Ribbon cutting; Governor Hochul attends

Funding

General fund, state pre-K aid ($1.36 million proposed; $10,000 per child rate) and district 'transfer to capital' for the playground

District told the Assemblyman its pre-K aid rate lags comparable districts.

Memorial Sixth Grade Center

Open; courtyard and plaza still to come

The Memorial building was renovated, mostly by district staff, to house all sixth graders. Courtyards and a veterans plaza are being named for local figures.

Next: Main courtyard targeted for completion by late March 2027
  1. Facilities committee prices courtyard and masonry work
  2. Board names the plaza and courtyards
  3. Courtyard 'outdoor room' estimated at $385,000
  4. Ribbon cutting and opening for the school year

Funding

Voter-approved capital project (2025) plus annual transfer to capital and donations for the plaza

Courtyard cost $385,000 per May 2026 facilities minutes.

Walt Whitman High School capital projects

Turf field open; media center nearly done

A second turf field (West Hills Field) opened, a TV and media production center is about 90% complete, boilers are being replaced, tennis courts will move, and a traffic signal is planned at West Hills Road and West Hills Court.

Next: Board and Town of Huntington finalize the traffic-signal agreement; media center opening this fall
  1. Facilities committee rejects turf bids as over budget
  2. Board rejects turf and media center bids and asks for rebids
  3. Turf field contract awarded
  4. Ribbon cutting for West Hills Field
  5. Media center reported about 90% complete

Funding

Voter-approved capital funding and annual transfer to capital ($6,667,275 in 2026-27)

Turf budget was about $1.5 million; the lowest first bid was $1,642,750.

Stimson nine-period day (under study)

Proposed, no decision

Stimson Middle School has costed three options to add a ninth period for world language, longer music classes, electives and lunch workshops. The fullest option would add 5.5 teachers.

Next: Governor's executive budget in early 2027 and the Feb. 10, 2027 budget overview meeting
  1. Curriculum council schedules a January discussion of a nine-period day at Stimson
  2. Costed options presented to the board
  3. Superintendent says it needs matching savings and depends on state aid

Funding

Not funded; would come from the general fund

Estimated $619,476 a year for the fullest option; about $506,844 and $112,632 for the others.

Response to State Comptroller credit-card audit

Corrective plan being drafted

The district must file a corrective action plan within 90 days of the September 2026 report. The audit committee will review it at a special meeting before it goes to the full board.

Next: Special audit committee meeting in early November 2026, then board adoption
  1. Board acknowledges the Comptroller's report
  2. Officials say fuel and credit cards were changed about three years ago and the corrective plan is being drafted

Funding

No separate funding; staff time

The audit covered 2,878 purchases worth $196,039.

Local elections & school board members

Elections & votes

Board electionScheduled

2027 annual budget vote and Board of Education election

South Huntington

The district's 2026/2027 board calendar lists the budget vote and election for Tuesday, May 18, 2027, 2 p.m. to 9 p.m. at Walt Whitman High School. Which trustee seats are up and the 2027-28 budget amount are not yet published.

Official source · verified Oct 20, 2026

Public votePassed

2026-27 school budget (Proposition 1)

South Huntington · $227,993,621

Voters approved the $227,993,621 budget with a 2.44% tax levy increase, 623 yes to 287 no, as certified by the board on May 19, 2026.

Official source · verified Oct 20, 2026

Public votePassed

Countrywood boiler replacement (Proposition 2)

South Huntington · $600,000

Voters approved reusing up to $600,000 left from the Walt Whitman boiler project for a new boiler at Countrywood Primary Center, 719 yes to 183 no, at no added cost to taxpayers.

Official source · verified Oct 20, 2026

Board electionPassed

May 19, 2026 Board of Education election (2 seats)

South Huntington

Incumbents Sidney Joyner and Andrew Bronson ran unopposed for two seats and were re-elected, per the board's certification of results.

Official source · verified Oct 20, 2026

School board members

Recent news

Figures marked verified come from the district's own budget slides, brochure, Comptroller report or recorded board meetings (auto-generated captions). Derived figures are marked context. Agendas and approved full-board minutes are kept in the district's BoardDocs system and could not be read for this page, so board actions come from recordings, committee minutes and posted documents.